  1. professional engineer Casey Jones Aug. 23 video (26 min.) covers Geologists of Wyoming presentation on Teton Pass Big Fill landslide
    youtu.be/yp6jMjA0gMM

  2. professional engineer Casey Jones Aug. 23 video (26 min.) covers Geologists of Wyoming presentation on Teton Pass Big Fill #WY22 #Wyoming landslide
    youtu.be/yp6jMjA0gMM
    #BigFill #TetonPass

  3. professional engineer Casey Jones Aug. 23 video (26 min.) covers Geologists of Wyoming presentation on Teton Pass Big Fill #WY22 #Wyoming landslide
    youtu.be/yp6jMjA0gMM
    #BigFill #TetonPass

  4. Geologists of Wyoming presentation on Teton Pass Big Fill landslide w/ geologist John Hebberger Jr, engineer Bob Hammond
    youtube.com/watch?v=MicEpNo2NrE

  5. Geologists of Wyoming presentation on Teton Pass Big Fill #WY22 #Wyoming landslide w/ geologist John Hebberger Jr, #WYDOT engineer Bob Hammond
    youtube.com/watch?v=MicEpNo2Nr
    #TetonPass #BigFill

  6. Geologists of Wyoming presentation on Teton Pass Big Fill #WY22 #Wyoming landslide w/ geologist John Hebberger Jr, #WYDOT engineer Bob Hammond
    youtube.com/watch?v=MicEpNo2Nr
    #TetonPass #BigFill

  7. Teton Pass reopens with temporary detour after three weeks
    KHOL/Jackson Hole Community Radio
    June 28, 2024
    Summary: contractor Scott Evans / Evans Construction ($500K Big Fill detour contract) discounts "armchair quarterback" skepticism, has full confidence in Evans 2.0 (vs. 55-y/o 1969 BF). has ≥ $6M fed emergency💰, more expected. fast-track: plan, design, bid, then 3 [short] months (Aug.-Nov.) to rebuild. Expected total cost: $30M.
    wyomingpublicmedia.org/open-sp

  8. Teton Pass reopens with temporary detour after three weeks
    KHOL/Jackson Hole Community Radio
    June 28, 2024
    Summary: contractor Scott Evans / Evans Construction ($500K Big Fill detour contract) discounts "armchair quarterback" skepticism, has full confidence in Evans #BigFill 2.0 (vs. 55-y/o 1969 BF). #WYDOT has ≥ $6M fed emergency💰, more expected. fast-track: plan, design, bid, then 3 [short] months (Aug.-Nov.) to rebuild. Expected total cost: $30M. #TetonPass #WY22
    wyomingpublicmedia.org/open-sp

  9. Teton Pass reopens with temporary detour after three weeks
    KHOL/Jackson Hole Community Radio
    June 28, 2024
    Summary: contractor Scott Evans / Evans Construction ($500K Big Fill detour contract) discounts "armchair quarterback" skepticism, has full confidence in Evans #BigFill 2.0 (vs. 55-y/o 1969 BF). #WYDOT has ≥ $6M fed emergency💰, more expected. fast-track: plan, design, bid, then 3 [short] months (Aug.-Nov.) to rebuild. Expected total cost: $30M. #TetonPass #WY22
    wyomingpublicmedia.org/open-sp

  10. Teton Pass reopens with temporary detour after three weeks
    KHOL/Jackson Hole Community Radio
    June 28, 2024
    Summary: contractor Scott Evans / Evans Construction ($500K Big Fill detour contract) discounts "armchair quarterback" skepticism, has full confidence in Evans #BigFill 2.0 (vs. 55-y/o 1969 BF). #WYDOT has ≥ $6M fed emergency💰, more expected. fast-track: plan, design, bid, then 3 [short] months (Aug.-Nov.) to rebuild. Expected total cost: $30M. #TetonPass #WY22
    wyomingpublicmedia.org/open-sp

  11. Teton Pass reopens with temporary detour after three weeks
    KHOL/Jackson Hole Community Radio
    June 28, 2024
    Summary: contractor Scott Evans / Evans Construction ($500K Big Fill detour contract) discounts "armchair quarterback" skepticism, has full confidence in Evans #BigFill 2.0 (vs. 55-y/o 1969 BF). #WYDOT has ≥ $6M fed emergency💰, more expected. fast-track: plan, design, bid, then 3 [short] months (Aug.-Nov.) to rebuild. Expected total cost: $30M. #TetonPass #WY22
    wyomingpublicmedia.org/open-sp