  1. “Still, as bad as these stories are — and they’re plenty bad — it’s important to remember that none of them really compare to the biggest #spending #scandal of Ford’s tenure: the ballooning cost of the #OntarioLine #subway project.” #Toronto #Ontario #DougFord www.thestar.com/news/gta/dou...

    Toronto’s Ontario Line now cos...

  2. #NorthAmerica has also suffered from a lack of #expertise in the #publicsector, he added, which means private sector companies wary of working with ill-experienced governments add #riskpremiums to contracts, driving up the price.” www.thestar.com/news/gta/dou... #OntarioLine #Toronto

    Toronto’s Ontario Line now cos...

  3. Spent the day around #Leslieville, it had been a while I had been around there. It’s quite nice and walkable

    I always just found it “far” from the rest of the city, while there’s no shortage of streetcar they always feel so slow.

    I saw the progress on the #OntarioLine stations, this will be transformative for the neighborhood. Had not realized how close each stations are.

    #ttc #toronto

  4. Yesterday I rode my bike up to the Millwood Bridge, which offers a really nice overlooking view of where Metrolinx is building a new subway bridge over the Don Valley. I wanted to see how the construction was coming along, and take a few pictures of the work-in-progress. It's honestly amazing to me how far apart the support pillars are for this bridge, and I have no idea how they are going to build the spans between them. But I look forward to finding out.

    I realized while taking pictures that the crane operator has to climb up right to the top every day. The cherry-pickers they use to get people up and down don't reach nearly that high.

    #Metrolinx #OntarioLine #Toronto

  5. I've just realized I'll probably be a senior when the Ontario Line is finally done. At least I'll pay less to use it.

    #OntarioLine #Toronto

  6. A crane suspends the long steel beam over the concrete-filled hole, then lowers it in. It took a bit of up/down wiggling, but it got all the way in.

    #OntarioLine

  7. Once the hole is filled with wet concrete, the augur is used to lift the steel cylinder out of the hole, leaving the concrete behind.

    In the background of the image you can see the giant steel beam waiting to be dropped into the hole.

    #OntarioLine

  8. I spent some time this morning watching the construction of the Ontario Line portal on Pape. This is where the new subway line will be switching from above ground to underground. Currently they are building the supporting structures underground before they start digging the actual portal. The process is pretty cool.

    First, they dig a very deep hole using a big augur. It has a drill in the middle, and a cylindrical outside that is left in the ground. In this picture you see the augur full of dirt that it dug from the hole. Behind it a cement truck is pouring concrete into the newly-drilled hole.

    #OntarioLine

  9. Some interesting slides from Metrolinx regarding the #Sammon #Fulton #Aldwych & #Pape area for the #OntarioLine construction.

  10. #Metrolinx finally admits what everyone has been expecting, the Ontario Line will open later than 2031

    It might also require closures of the DVP for some crucial engineering work (the line will go over the freeway)

    theglobeandmail.com/gift/078c2

    #OntarioLine #Topoli

  11. On my way home from Mount Dennis station I took the UPX to Union, then the Lakeshore East GO train so I could check out the construction of the Ontario Line between Union and Pape.

    Most of the track bed is now laid down. The concrete for the Dundas bridge is not yet poured. The Logan bridge is in, but not surfaced yet.

    The Don River bridge is half-installed (just the east half), and the foundations for East Harbour Station are well underway.

    #toronto #OntarioLine

  12. This is cool -- metrolinx.com/en/projects-and- is the Ontario Line Truck Route Safety Plan, complete with lots of detailed maps of all of the truck routes for all of the various projects around the Ontario Line.

    I'm guessing -- three years of construction, and then another three years of Why Isn't It Open Yet, Metrolinx?

  13. @waleedkhogali: Join us in demanding a bold approach to development that puts people first.

    🔗 Follow the movement: @BOLDCoalitionTO | #BOLDCoalition #Corktown #OntarioLine #CommunityFirst #TransitJustice

    ---

  14. Ontario Line construction site mismanagement led this week to someone being run over in a crosswalk just blocks from my home, in a residential area with hundreds of kids.

    The truck wasn’t following the official route, and this petition from the Pape Village Safety Action Council is pushing for better.

    Live in Ontario? Your tax dollars are paying for this. Please consider signing and sharing.

    chng.it/Hpx86btDCV

    #ONPoli #TOPoli #Metrolinx #EastYork #TorontoDanforth #Toronto #OntarioLine

  15. View of the Don Valley showing stairs from Street level down to the DVP. Here comes the .

  16. Someone is not having a good day.

  17. It's been announced today that the Queen St detour track work is complete and the Queen street shuttle bus detour will stop on October 6th. The 501 streetcar can resume its operations along downtown.

    The streetcar will still be on a new detour route until the end of construction of the #OntarioLine downtown (scheduled for 2027, but I suppose this is still TBD)

    stevemunro.ca/2024/09/27/ttc-s

    #ttc #topoli #toronto #metrolinx

  18. I wish the Ontario Line Image Collective (self-described as “artists making images of communities & places affected by Toronto's new subway line”) had a website in addition to just an Instagram profile. #Toronto #OntarioLine instagram.com/ontario_line_ima

  19. Investigating the machinery at the Sammon/Pape location of the . Apparently this equipment is used with slurry to gouge out deep, rectangular holes. They then stuff a huge rebar box into the hole, and fill it with concrete.

    If my Dad was still with us, he'd be fascinated.

  20. Demolition at Pape and Danforth. It's happening.

  21. There used to be a KFC on Pape near me. This is what's left tonight.

    It's going to be some sort of staging area for the .

  22. The demolition continues near Pape station for the .