  1. PORT TALBOT: Government pays EY £1m to vet Tata’s plea for more furnace money

    The UK Government is paying accountancy firm EY £1m to check Tata Steel‘s request for more public money to finish its new furnace in Port Talbot.

    Known as an electric arc furnace, it melts scrap steel using electricity. It is the heart of the £1.25bn plan to keep steel being made at the Port Talbot works after the last blast furnace closed in 2024.

    Tata says the furnace will be able to make 3.2 million tonnes of steel a year.

    One of the fabricated furnace components, made by Italian firm Tenova, ahead of shipping to Port Talbot (Image: Tata Steel)

    Sky News reported on Thursday that Tata’s request is understood to run to hundreds of millions of pounds, on top of the £500m the UK Government has already committed to the project.

    The Government’s business department awarded EY the contract on 10 August, for “independent financial due diligence and commercial analysis”. It runs until August 2027.

    Tender documents are reported to describe the work as supporting the Government’s assessment of Tata’s request for additional support for the furnace.

    A grid connection running months late

    The furnace was due to be making steel by early 2028. Then National Grid told Tata in June that the high-voltage connection it needs was running six to eight months late.

    Tata is understood to now expect the furnace to be running in late 2028 or early 2029, and to have worked out that higher costs and lost sales from the delay will push the overall bill up significantly.

    When the delay first surfaced, Stephen Kinnock, the Aberafan Maesteg MP who is now Secretary of State for Wales, said there was “no formal change in the timetable at this stage”.

    Thousands of jobs already gone

    The furnace plan was meant to protect 5,000 steel jobs across the UK, but around 2,500 are reported to have already gone in the switch.

    One of the Port Talbot blast furnaces, the last of which closed in 2024 (Image: Tata Steel)

    Cheap imports have added to the pressure. Tata warned in June that the UK’s new import limits left Port Talbot exposed.

    The furnace is also politically high-profile: Prime Minister Andy Burnham chose Port Talbot for his first official visit to Wales in August.

    Ministers are not saying what they make of Tata’s request. The UK Government has declined to comment, saying any discussions with a private company “would be commercially sensitive”.

    Tata bosses are reported to have confirmed last month that talks were under way.

    The Port Talbot steelworks (Image: Tata Steel)

    Meanwhile, the first kit is arriving

    On site, the work is moving. The first sections of the acid tanks for the line that cleans the surface of steel strip, known as a pickle line, arrived at the works this week, Tata says.

    Each section weighs around 10 tonnes and came in through the Port of Sheerness. The company says they are the first of a growing number of major deliveries due over the coming weeks and months for both the pickle line and the furnace.

    Mark Jones, from the pickle line project team, said: “It’s been a long, long time coming. We’ve been on the project now for around 18 months and it’s all been about the planning stage up until now.”

    He said it was “the first time we’ve actually seen something happening from the mechanical aspect”.

    Related stories from Swansea Bay News

    GREEN STEEL DELAY: ‘No formal change’ to furnace timetable, as row breaks out over who knew what
    The June row over when the grid delay was first known.

    PORT TALBOT: Tata is building its new pickle line in a bay the June fire left without a roof
    Inside the bay where the acid tanks will go.

    GREEN STEEL: Tata warns new UK import rules leave Port Talbot exposed
    The import quotas Tata says do not go far enough.

    More on Tata Steel from Swansea Bay News
    Every story on the works and the transition.

    #electricArcFurnace #featured #greenSteel #NationalGrid #PortTalbot #PortTalbotSteelworks #ProjectInvictus #StephenKinnockMP #TataSteel #UKGovernment
  2. Port Talbot grid batteries trial: National Grid, Celtic Freeport plan to speed up connections

    New factories in and around Port Talbot could be plugged into the electricity network sooner under a trial…
    #EuropeSays #Britain #Europe #EU #NationalGrid #CelticFreeport #electricarcfurnace #energy #NeathPortTalbot #NetZeroIndustryWales #PortTalbot #PortTalbotSteelworks #TataSteel
    europesays.com/britain/135563/

  3. PORT TALBOT: The grid firm that’s late plugging in the furnace says batteries could get the next factories connected sooner

    New factories in and around Port Talbot could be plugged into the electricity network sooner under a trial of grid-controlled batteries, National Grid says, in a region where even the £1.25bn electric arc furnace is waiting for its connection.

    National Grid Electricity Distribution, Net Zero Industry Wales and the Celtic Freeport are launching what they call a multi-year innovation programme to squeeze more out of the existing wires while bigger upgrades are built.

    It is the distribution side of National Grid, which runs the local network, rather than the transmission arm building the furnace’s high-voltage connection, a job it told Tata in June was running six to eight months late because of ground conditions and planning.

    Batteries the grid switches on and off

    The first project will test whether batteries controlled by the network operator, rather than by whoever owns them, can smooth out the peaks and troughs of supply and demand and free up capacity on the network.

    If it works, the company says, renewable projects and industrial customers could connect sooner instead of waiting for new substations and cables to be built.

    “Our role is to make sure customers can access the electricity they need to grow, decarbonise and invest with confidence,” said Roisin Quinn, president of National Grid Electricity Distribution. “This programme is a direct response to what industrial businesses in South Wales have told us they need.”

    “Electricity access is a bottleneck”

    Ben Burggraaf, chief executive of Net Zero Industry Wales, put it more bluntly. “Electricity access is a bottleneck and accelerating access is critical in attracting investment,” he said. The programme, he added, would “trial concepts to get more out of existing capacity” and “maximise local generation”.

    The idea grew out of the South Wales Industrial Dialogue, in which more than 30 industrial firms worked with the two organisations and came up with more than 25 possible fixes, from earlier connections to more flexible use of the wires already in the ground.

    The Freeport’s Investment Zone status means it can be first to test them, said its interim chief executive Cathy Hall. “As we move into the delivery phase for our projects, exploring innovative solutions to known power constraints will be crucial,” she said.

    Why the queue matters here

    The problem is not new. When the body that plans Britain’s grid held a forum in Swansea in June, its head of Wales listed “uneven connectivity, grid constraints and fuel poverty” among the obstacles, and Burggraaf told the same room Wales could be a clean energy hub only if the grid investment followed.

    The furnace is the case everyone points to. The transmission works need two new substations and miles of cable, and the former Aberavon MS who chaired the Senedd’s steel group has said the furnace may not run until autumn 2028, calling for National Grid to face penalties if it slips further.

    Others have found ways round the queue. The data centre approved at Margam in May will draw its power through a private wire from the biomass plant next door, skipping the grid altogether, in a boom that Senedd researchers say will need more power than Wales’s entire solar fleet.

    The Freeport covers Port Talbot and Milford Haven, and its pitch rests on power-hungry newcomers, from the floating wind hub ABP is designing at the docks with £64m of UK Government money to hydrogen and the supply chain behind them.

    “Working closely with customers is central to how we innovate,” said Emily Spearman, innovation director at National Grid Electricity Distribution, who said the partnership was a chance to test approaches “that can accelerate decarbonisation, unlock growth and help shape the future energy system”.

    The three organisations have yet to sign the memorandum of understanding setting out how they will work together, and have not put a date on the first battery trial or said where the batteries would go.

    Related stories from Swansea Bay News

    GREEN STEEL DELAY: Former Aberavon MS says National Grid should face penalties over delayed electric furnace connection
    David Rees on the connection that could push the furnace to autumn 2028.

    ENERGY: South Wales could be a clean power giant, so why are bills still high, and what’s holding it back?
    The June forum where the grid kept coming up as the wall.

    DATA CENTRES: A new industrial revolution is rising on south Wales’s old factory floors, and it arrives hungry and thirsty
    The Margam scheme that skipped the grid queue with a private wire.

    More energy coverage from Swansea Bay News
    Every story on the wires, the pylons and the connections.

    Author

    Kit Peters

    Kit Peters is a journalist and the editor of Swansea Bay News, covering Swansea, Neath Port Talbot and Carmarthenshire since 2020.

    #CelticFreeport #electricArcFurnace #energy #NationalGrid #NeathPortTalbot #NetZeroIndustryWales #PortTalbot #PortTalbotSteelworks #TataSteel
  4. Hyundai Steel-POSCO U.S. Mill Hosts Community Event in Louisiana

    A family of Donaldsonville residents enjoys the “HPLS Community Day” event. Hyundai Steel Hyundai Steel (004020) and POSCO’s…
    #EuropeSays #Korea #KR #POSCO #automotivesteelsheet #Donaldsonville #electricarcfurnace #HPLS #HyundaiSteel #Louisianasteelmill
    europesays.com/korea/148087/

  5. POSCO Invests 480 Billion Won in New Auto Steel Plant

    A view of POSCO’s Gwangyang Steelworks. /POSCO POSCO is investing 480 billion won ($350 million) to expand production…
    #EuropeSays #Korea #KR #POSCO #8CGL #automotivesteelsheet #electricarcfurnace #GwangyangWorks #hot-dipgalvanizedsteel #HyperNO
    europesays.com/korea/146771/

  6. Hyundai Steel’s U.S. Mill to Be America’s Greenest, CEO Says

    Kim Hyung-jin, executive vice president and head of Hyundai Steel’s North American steel business division, and chief executive…
    #EuropeSays #Korea #KR #HyundaiMotor #automotivesteelsheet #directreducediron #electricarcfurnace #HPLS #Hyundai #HyundaiSteel #Louisianasteelmill #POSCO
    europesays.com/korea/145215/

  7. Hyundai Steel’s U.S. Mill Must Deliver for Both Nations

    Key attendees break ground at the groundbreaking ceremony for the Hyundai Steel-POSCO Louisiana electric arc furnace steel mill…
    #EuropeSays #Korea #KR #POSCO #automotivesteelsheet #DomesticProductionTaxCredit #electricarcfurnace #HyundaiSteel #Louisianasteelmill #U.S.steeltariffs
    europesays.com/korea/144971/

  8. Hyundai Steel Targets U.S. AI Data Center and Power Grid Market

    Hyundai Motor Group Chairman Chung Euisun answers reporters’ questions at the groundbreaking ceremony for the Hyundai Steel-POSCO Louisiana…
    #EuropeSays #Korea #KR #HyundaiMotor #AIDataCenters #electricarcfurnace #Hyundai #HyundaiSteel #HyundaiSteelLouisianaplant #powerinfrastructure #rebarexports #U.S.steeltariffs
    europesays.com/korea/144825/

  9. Hyundai, POSCO Break Ground on $5.8 Billion U.S. Steel Mill

    Key attendees break ground at the groundbreaking ceremony for the Hyundai Steel-POSCO Louisiana electric arc furnace steel mill…
    #EuropeSays #Korea #KR #Hyundai #electricarcfurnace #HPLS #HyundaiGroup #HyundaiMotorGroup #HyundaiSteel #Louisianasteelmill #POSCO #specialtysteel #U.S.steeltariff
    europesays.com/korea/144807/

  10. U.S. Hails Hyundai Steel, POSCO Mill in Louisiana

    Louisiana Governor Jeff Landry speaks at the groundbreaking ceremony for the Hyundai Steel-POSCO Louisiana Steel (HPLS) electric arc…
    #EuropeSays #Korea #KR #POSCO #electricarcfurnace #HPLS #HyundaiSteel #JeffLandry #Louisianasteelmill #U.S.Manufacturing
    europesays.com/korea/144803/

  11. Rivals at home Hyundai, Posco break ground in Louisiana for joint steel mill

    $5.8b steelworks part of $26b US investment pledge made by Hyundai Motor Group Chairman Chung Euisun Hyundai Motor…
    #EuropeSays #Korea #KR #HyundaiMotor #BatonRouge #ChungEuisun #Donaldsonville #electricarcfurnace #HPLS #Hyundai #HYUNDAI-POSCOLouisianaSteel #JeffLandry #Kia #Korean #Louisiana #POSCO #Steel #steelmaking
    europesays.com/korea/144491/

  12. Euisun Chung Eyes Supplying Steel from U.S. Plant to SpaceX Rockets, Hints at Deploying Atlas Robots — BigGo Finance

    Euisun Chung, chairman of Hyundai Motor Group, said he wants to supply steel produced at the group’s steel…
    #EuropeSays #Korea #KR #HyundaiMotor #Atlas #directreducediron #electricarcfurnace #ElonMusk #EuisunChung #Hyundai #HyundaiMotorGroup #HyundaiSteel #Louisianasteelmill #POSCO #SpaceX
    europesays.com/korea/144333/

  13. Hyundai Chairman Sees Tariff, Quality Synergy From U.S. Steel Mill

    Hyundai Motor Group Chairman Chung Euisun answers reporters’ questions at the groundbreaking ceremony for the Hyundai Steel-POSCO Louisiana…
    #EuropeSays #Korea #KR #HyundaiMotor #automotivesteelsheet #electricarcfurnace #EuisunChung #Hyundai #HyundaiMotorGroup #HyundaiSteel #Louisianasteelmill #POSCO
    europesays.com/korea/143977/

  14. Hyundai Motor CEO Says Louisiana Steel Will Go Into Every Model

    Hyundai Motor President and CEO José Muñoz. Hyundai Motor DONALDSONVILLE — José Muñoz, president and chief executive of…
    #EuropeSays #Korea #KR #HyundaiMotor #automotivesheetsteel #electricarcfurnace #Hyundai #HyundaiSteel #JoséMuñoz #louisianasteelplant #POSCO
    europesays.com/korea/143957/

  15. Chang In-hwa: POSCO-Hyundai Steel U.S. Mill to Be World’s Most Competitive

    POSCO Group Chairman Chang In-hwa answers reporters’ questions at the groundbreaking ceremony for the Hyundai Steel-POSCO Louisiana Steel…
    #EuropeSays #Korea #KR #POSCO #ChangIn-hwa #directreducediron #electricarcfurnace #HPLS #HyundaiSteel #Louisianasteelmill
    europesays.com/korea/143809/

  16. Hyundai Steel Breaks Ground on $5.8 Billion U.S. Electric Arc Furnace Mill

    A rendering of the Hyundai Steel-POSCO Louisiana electric arc furnace steel mill (HPLS). Hyundai Steel Hyundai Steel (004020)…
    #EuropeSays #Korea #KR #POSCO #automotivesteelsheet #electricarcfurnace #HPLS #HyundaiSteel #Louisianasteelmill #U.S.steeltariffs
    europesays.com/korea/143719/

  17. Hyundai Steel Q2 2026 Results: Sales Up, Profit Down, US Plant Construction Ahead – News and Statistics

    Aug 10, 2026 Hyundai Steel, the South Korean steelmaking unit of automakers Hyundai Motor and Kia, posted a…
    #EuropeSays #Korea #KR #Hyundai #4.42milliontonnes #AIDataCenters #electricarcfurnace #GMKCenter #HyundaiGroup #HyundaiMotorGroup #HyundaiSteel #Louisianasteelworks #operatingprofit #Q22026 #semiconductorsteel #steelsales
    europesays.com/korea/114750/

  18. POSCO, Hyundai Steel Seek Breakthrough in AI Data Centers and Power Infrastructure Amid Race for New Steel Demand — BigGo Finance

    South Korea’s steel industry, suffering from the double blow of an onslaught of low-cost Chinese steel and tariff…
    #EuropeSays #Korea #KR #POSCO #AIDataCenters #electricarcfurnace #electricalsteelsheet #EUsafeguards #HyundaiSteel #low-costChinesesteel #MordorIntelligence #Pos-H #PosMAC #powerinfrastructure #U.S.tariffs
    europesays.com/korea/110350/

  19. 1 Stock That Could Surge as Canada Launches Tariff Retaliation

    Written by Amy Legate-Wolfe at The Motley Fool Canada A 25% tariff can change where billions of dollars…
    #Canada #AlgomaSteel #Americansteel #electricarcfurnace #FoolCanada
    europesays.com/canada/137662/

  20. POSCO Group Strategic Plan: Sixfold Profit Growth by 2035 via Lithium and Renewables – News and Statistics

    Jul 6, 2026 POSCO Group, a major South Korean industrial conglomerate, has outlined plans to boost its operating…
    #EuropeSays #Korea #KR #POSCO #ChangIn-hwa #electricarcfurnace #InvestorDay #lithium #LNG #POSCOGroup #renewableenergy #SouthKorea #Steel #technology
    europesays.com/korea/76151/

  21. GREEN STEEL: Llanelli firm lands key contract on Port Talbot’s £1.25bn transformation — with work starting on site today

    A Llanelli construction firm has landed a key contract on the £1.25bn transformation of Port Talbot steelworks — with work beginning on site today.

    Morganstone, founded in Llanelli and now based in Swansea, will deliver the civil and structural package for the works’ new pickle line, winning the contract through a competitive tender.

    It is the company’s first contract with Tata Steel — and its first step onto the biggest industrial site in Wales.

    Morganstone managing director Andrew Pettigrew (left) shakes hands with Andrew McGregor, programme manager for Project Invictus, as the Llanelli firm’s first contract with Tata Steel is confirmed (Image: Tata Steel)

    A pickle line cleans hot-rolled steel by submerging it in hydrochloric acid to strip away the scale that forms on its surface, preparing it for the mills that roll and coat the finished product. Tata has previously described the kit as the unsung hero of steelmaking.

    The contract marks the shift from demolition and enabling works into the main construction phase on the line, which Tata broke ground on last autumn.

    Andrew McGregor, programme manager for Project Invictus — Tata’s name for the transformation — said the appointment was a turning point for the project.

    “This marks the start of the construction phase for the new Pickle Line project in Tata Steel UK. It’s a really positive feeling to know we are moving away from demolition and enabling works into construction,” he said.

    He said the Morganstone contract covered the installation of the line’s process section, which is “on the critical path” because of the amount of structural steelwork to be installed on the new foundations — ultimately supporting the pickling and rinse tanks themselves.

    “The team now continues to work on the remaining civil and structural packages, as there is no time to lose in placing the remaining contracts, with new Pickle Line equipment scheduled to start arriving imminently,” he added.

    Mark Davies, who leads the civil and structural works on the project’s mills programme, said in a video published by Tata that securing “a regional contractor with a local workforce” had been important, with the foundation work for one zone of the new line sitting on the critical path.

    He said Morganstone’s past projects, quality and programme — and the work ethic of its project management team through the tender — had stood out.

    When ground was broken on the new line last September, it was slated to be in place during 2026 — with the main construction phase now only beginning.

    The contract also comes weeks after fire damaged the works’ existing pickle line — which Morganstone’s managing director Andrew Pettigrew confirmed remains out of action — with Tata routing work to its Llanwern site while it recovers. The replacement line was planned long before the blaze.

    Morganstone was founded in 2008 by Ian Morgan and has grown from its Dafen headquarters into one of Wales’ busier contractors — best known for housing and public buildings, from waterfront apartments at SA1 to the planned 186-home regeneration at Penplas.

    Morganstone managing director Andrew Pettigrew on site at Port Talbot (Image: Tata Steel)

    Mr Morgan, the firm’s chairman, said: “We are delighted to have been appointed by Tata Steel UK to deliver this important project. The award reflects the capability, experience and commitment of our team and is a significant contract for Morganstone to be involved with.”

    “We understand the importance of this project and look forward to working collaboratively with Tata Steel UK to deliver it safely, efficiently and to the highest standards,” he added.

    Morganstone and Tata Steel staff outside the site offices at Port Talbot ahead of work beginning on the new pickle line (Image: Tata Steel)

    Mr Pettigrew said the contract was one the firm had long chased.

    “Working with Tata is something which we’ve been trying to get into for a number of years,” he said, adding that the firm had spent the last three months working through the design and tender process.

    Work starts on site today, he said — breaking out the existing slabs first, with piling and the steel frames to follow.

    And the job will be built by local hands. “We don’t leave Wales,” said Mr Pettigrew, explaining that almost all the firm’s work sits along the M4 corridor around Swansea — with the frame contractor and groundworker for the pickle line both Swansea-based, and the steel frame partner in Cardiff.

    Teams from Morganstone and Tata Steel discuss the project inside the Port Talbot works (Image: Tata Steel)

    The new pickle line is one strand of Project Invictus at Port Talbot, whose centrepiece is a 3.2 million-tonne-a-year electric arc furnace that will melt scrap steel with electricity rather than coal — backed by £500m of UK Government funding. The furnace itself has been built and is on its way to south Wales.

    The transformation followed the closure of the town’s blast furnaces in 2024 with the loss of around 2,000 jobs, and the furnace’s start-up — due in late 2027 or early 2028 — could slip by up to eight months after National Grid connection delays.

    Work across the site has accelerated over the past year, from major groundwork and piling across the furnace area to new scrap-handling infrastructure and grid connection works — with around 1,200 people expected on site at peak.

    The Llanelli firm will work alongside Tata and the wider Project Invictus team throughout the delivery of the line.

    Related stories from Swansea Bay News

    Tata Steel begins new project at Port Talbot in £1.25bn green plan
    Ground was broken on the new pickle line last autumn, led by Sir Robert McAlpine with regional firms alongside.

    GREEN STEEL: Port Talbot’s giant new furnace is built and on its way
    The electric arc furnace at the heart of the transformation has been fabricated and is being shipped to south Wales.

    GREEN STEEL: Tata ‘confident’ supply will hold after Port Talbot fire
    The blaze at the works’ existing pickle line saw work routed to Llanwern while the site recovers.

    #electricArcFurnace #greenSteel #industry #Morganstone #PickleLine #PortTalbot #PortTalbotSteelworks #ProjectInvictus #TataSteel
  22. POSCO Holdings Inc. (PKX) a High Dividend Mining Stock Poised for Low Carbon Steel Opportunities

    Posco Holdings Inc. (NYSE:PKX) is one of the mining stocks with the highest dividends. shutterstock_284891573.jpg Christian Lagerek/Shutterstock.com On…
    #EuropeSays #Korea #KR #POSCO #electricarcfurnace #miningstocks #POSCOHoldings #SouthJeollaProvince #steelproduction
    europesays.com/korea/71107/

  23. GREEN STEEL: Tata warns new UK import rules leave Port Talbot exposed

    Tata Steel has warned that new UK rules meant to curb cheap steel imports do not go far enough to protect British producers, raising fresh concerns over the future of its Port Talbot operations.

    The company was responding to the UK Government’s final steel import quota framework, published today, which takes effect from 1 July.

    The measures are intended to shield UK steelmakers from a global glut of cheap steel by limiting how much can be imported tariff-free, with higher tariffs on imports above those limits.

    But Tata Steel UK chief executive Rajesh Nair said the final quotas still allowed too much overseas steel into strategically important parts of the UK market.

    “We do not believe the final quota levels published today reflect UK market conditions or the pressures facing the domestic steel industry,” he said.

    Tata Steel UK chief executive Rajesh Nair. (Image: Tata Steel UK)

    He said several categories of steel would still face significant import competition, “exposing domestic production and supply chains to continued pressure.”

    Mr Nair said the company was “disappointed by elements of the final framework” and “very concerned about the implications for the long-term competitiveness, sustainability, growth and future investment outlook for the UK steel sector.”

    He said that if the government wanted UK producers to supply half of the country’s steel demand, the quota arrangements would need to offer stronger support, and called on ministers to reconsider parts of the framework.

    The trade body UK Steel was also critical. Its director of trade and economics, Peter Brennan, said the new quota had in some areas “made the situation worse for UK producers,” singling out galvanised steel, where he said the allocation for Vietnam had been more than tripled.

    He said there had been “an opportunity missed in key areas” that would leave parts of the UK supply chain exposed to heavily subsidised imports.

    The government has defended the measures. From 1 July, tariff-free steel imports will be cut and tariffs on imports above the new limits will rise, in a framework ministers say is designed to protect UK steelmaking while still allowing manufacturers to source specialist steels not made in Britain.

    It has exempted 11 categories of steel where there is no UK alternative, and has said it wants domestic producers to be able to meet up to half of UK demand.

    The government has also pointed to the support it has already put into the industry, including £500m towards the new electric arc furnace being built at Port Talbot.

    Steelworks at Port Talbot

    The intervention matters for Wales, where Tata is part-way through a major transformation of the Port Talbot works.

    The company closed its blast furnaces in 2024, with the loss of around 2,000 jobs, and is replacing them with a new electric arc furnace expected to produce lower-carbon “green” steel.

    Only yesterday, Tata was showing off a year of transformation as the giant new furnace neared completion.

    But the transition has not been smooth. Earlier this month, the firm warned the project could be delayed by up to eight months because of a hold-up connecting it to the electricity grid.

    Tata said it recognised the work the government had put into the framework during what it called an exceptionally challenging period for global steel, but urged ministers to keep working with the industry and to reconsider parts of the final arrangements.

    Related stories from Swansea Bay News

    Port Talbot’s giant new furnace is built and on its way
    Tata shows off a year of transformation at the steelworks.

    Port Talbot’s £1.25bn furnace could be delayed over power hold-up
    The grid connection problem threatening the project’s timetable.

    Welsh Government demands UK action over steel trade threat
    Earlier warnings that Welsh steel needed protection from cheap imports.

    #electricArcFurnace #greenSteel #PortTalbotSteelworks #RajeshNair #steelImports #TataSteel
  24. POSCO Completes Korea’s Largest EAF to Advance Green Steel

    POSCO Holdings Inc. PKX is accelerating its transition toward low-carbon steelmaking with the completion of South Korea’s largest electric…
    #EuropeSays #Korea #KR #POSCO #carbonemissions #ConsensusEstimate #electricarcfurnace #steelmaking #ZacksInvestmentResearch
    europesays.com/korea/63919/

  25. GREEN STEEL: Port Talbot’s giant new furnace is built and on its way — as Tata shows off a year of transformation

    The centrepiece of Tata Steel’s £1.25bn transformation of Port Talbot — its giant new electric arc furnace — has been built and is now making its way to south Wales.

    In a project update, the company said the main components of the furnace had been fabricated and were beginning their journey to Port Talbot from sites around the world.

    The furnace has been designed and made by the Italian metals technology firm Tenova, and is billed as one of the largest of its kind ever built, with a main shell measuring more than nine metres across.

    Once running, it will be capable of producing 3.2 million tonnes of steel a year, melting scrap using electricity rather than the coal-fired blast furnaces that defined the site for generations.

    The update came in the latest instalment of Tata’s own video series charting the rebuild, in which a presenter and project director tour the site a year on from when much of it was still open ground.

    Excavators at work on the transformed Port Talbot site, where open ground is being prepared for the new plant. Image: Tata Steel

    Tata’s project director said the big parts were ready to ship, with roughly a two-month sailing ahead of them before they arrive to be offloaded.

    The components are being delivered in 11 separate lots, spread out over the coming year, the company said.

    According to Tata, the wider project is “on plan” and broadly on time, with the director describing the progress over the past year as a “morale booster” for the workforce.

    Molten metal at Port Talbot — the electric arc furnace will melt scrap using electricity rather than coal. Image: Tata Steel

    Around 1,200 people are expected to be working on the site at peak, across civil, mechanical, electrical and piping work.

    The video showed the scale of the groundworks — including a former cooling lagoon partly filled with some 220,000 tonnes of stone, and a separate area cleared of around 400,000 tonnes of material.

    The cooling water lagoon beside the steelworks, part of which is being filled in as work progresses. Image: Tata Steel

    The footage also showed work on the site’s future scrap yard, which will handle around 70,000 tonnes of scrap a week to feed the new furnace

    An aerial view of the site earmarked for the scrap metal yard, which will feed the new electric arc furnace. Image: Tata Steel

    Nearby, contractors for National Grid are piling the ground for a 275,000-volt substation that will power the furnace, on land the grid operator now leases from Tata.

    The furnace site itself was where the UK’s Business and Trade Secretary, Peter Kyle, launched the government’s Steel Strategy in March, and where a groundbreaking ceremony was held in July last year.

    Tata’s confident tone follows a turbulent few weeks for the project, however.

    Earlier this month, Swansea Bay News reported that the furnace could be delayed by up to eight months over a hold-up in its power connection, prompting cross-party calls for answers and a row over who knew what, and when.

    An earlier shipment of furnace parts had also been pushed back by several weeks, with reports linking the delay to rising shipping costs amid tensions in the Middle East.

    Cleared ground inside the works where legacy equipment has been stripped out. Image: Tata Steel

    The switch to electric arc steelmaking, backed by £500m of UK Government funding, is central to Tata’s plan to cut emissions at Port Talbot — but it came at the cost of thousands of jobs when the blast furnaces closed.

    A full video tour of the site is available on Tata Steel’s YouTube channel.

    Related stories from Swansea Bay News

    Port Talbot’s £1.25bn furnace could be delayed by up to eight months over power hold-up
    The grid connection problem that put the project’s timetable in doubt.

    Cross-party calls for answers over Port Talbot furnace setback
    Politicians press Tata and National Grid over the delay.

    Tata ‘confident’ furnace project unaffected after Port Talbot fire
    The company’s response after a fire at the steelworks this month.

    #electricArcFurnace #greenSteel #NationalGrid #PeterKyle #PortTalbotSteelworks #TataSteel #Tenova
  26. POSCO Accelerates Transition to Decarbonized Production System with Completion of Korea’s Largest Electric Arc Furnace

    KRW 600 billion invested in Gwangyang EAF with an annual capacity of 2.5 million tons… Reducing carbon emissions…
    #EuropeSays #Korea #KR #POSCO #EAF #electricarcfurnace #low-carbonsteel
    europesays.com/korea/60897/

  27. POSCO Completes Korea’s Largest Electric Arc Furnace in Gwangyang

    Aerial view of POSCO’s Gwangyang Steelworks/POSCO POSCO has completed a large electric arc furnace in Gwangyang, South Jeolla…
    #EuropeSays #Korea #KR #POSCO #carbon-reduction #CBAM #electricarcfurnace #GwangyangSteelworks #hydrogen-basedsteelmaking #hyrex #low-carbonsteel
    europesays.com/korea/55816/

  28. GREEN STEEL DELAY: Cross-party calls for answers over Port Talbot furnace setback as politicians press Tata and National Grid

    The delay to Port Talbot’s new electric arc furnace has prompted a cross-party call for answers at the Senedd, with members pressing both Tata Steel and the National Grid.

    The £1.25bn furnace, central to the future of steelmaking in the town, could be held up by up to eight months because of delays to the power infrastructure the National Grid is building to run it.

    Elyn Stephens, Plaid Cymru MS for Afan Ogwr Rhondda, said the delay was “another blow to the communities I represent”.

    She said it meant a longer wait for much-needed jobs and economic regeneration, and created further uncertainty for local residents.

    “I have contacted Tata directly this afternoon and will be making further representations tomorrow,” she said.

    “People in Port Talbot deserve honesty and transparency about when this development is expected to be delivered.”

    Huw Irranca-Davies, Labour MS for Afan Ogwr Rhondda, said the news — coming on top of the recent fire at the works — had caused understandable concern for the workforce, unions and the wider supply chain across Wales.

    He said he had already been in contact with Tata to seek assurances that the transition to electric steelmaking was proceeding and that the jobs relying on it were protected.

    Irranca-Davies said he understood Tata might issue a further statement in the coming days, which he hoped would offer reassurance that the difficulties would be overcome.

    He added that he had accepted a place alongside other local members on the Tata Transition Board, and had asked the UK government and the new Welsh Government — including the Cabinet Minister for Enterprise, Adam Price — to support the move to electric arc production.

    The delay also drew comment from the Welsh Conservatives. Janet Finch-Saunders, the party’s shadow minister for enterprise, connectivity and energy, called the situation “deeply concerning”.

    She said the furnace was “a vital investment for the future of Welsh steelmaking, jobs and economic growth”, and that the National Grid and the UK government “must urgently work together to resolve these connectivity issues and ensure this strategically important project is delivered without further delay”.

    The interventions follow a similar call from David Rees, the former Aberavon MS who chaired the Senedd’s cross-party group on steel, who said the National Grid should face penalties if the connection slipped further.

    The electric arc furnace is designed to make lower-carbon “green steel” by melting scrap rather than burning coal, replacing the blast furnaces that closed in 2024 with the loss of around 2,000 jobs — part of a wider £1.25bn transformation of the works.

    It relies on a major grid upgrade — including a major substation expansion approved by the council earlier this year — which the National Grid has said is running late because of ground conditions and planning issues.

    Tata has said the project timeline “continues to evolve” and that it is working to deliver the furnace “safely and as quickly as possible”.

    Related stories from Swansea Bay News

    GREEN STEEL: Port Talbot’s £1.25bn furnace could be delayed by up to eight months over power hold-up
    Tata’s warning over the delayed grid connection.

    GREEN STEEL DELAY: Former Aberavon MS says National Grid should face penalties
    David Rees calls for penalties if the connection slips further.

    ‘Green power’ boost for Port Talbot as council green-lights major substation expansion
    The substation upgrade central to powering the new furnace.

    STEELWORKS FIRE: Tata says blaze restricted to ‘confined area’ of Cold Mill
    A separate fire at the site earlier this month.

    #AfanOgwrRhondda #electricArcFurnace #ElynStephens #featured #HuwIrrancaDaviesMS #industry #JanetFinchSaundersMS #NationalGrid #PlaidCymru #TataSteel #WelshConservatives
  29. GREEN STEEL DELAY: Former Aberavon MS says National Grid should face penalties over delayed electric furnace connection

    The delay to Port Talbot’s new electric arc furnace — caused by the National Grid’s own infrastructure works running behind — is worse than feared, according to the former politician who spent years scrutinising the project.

    David Rees, the former Labour MS for Aberavon and a long-standing chair of the Senedd’s cross-party group on steel, was responding to Tata Steel’s warning that the £1.25bn furnace could be held up by up to eight months, after the National Grid told the company its connection project was running late.

    The grid operator needs to build two new substations and lay miles of underground cabling to power the furnace, and has blamed ground conditions and planning issues for the hold-up.

    His comments relate to that grid connection — a separate issue from the recent fire at the site’s cold mill.

    Rees said he had questioned the grid connection from the very start of the project.

    “One of the questions I asked Tata at the beginning of the EAF project was about the grid connection, and were they sure that it would be ready by late 2027,” he said.

    He said he had been told repeatedly that the National Grid had given assurances the work would be delivered on time.

    “It’s a question I continued to ask every time we met to discuss the project, and every time I received the same assurances,” he said.

    In recent months, he said, workers had begun raising concerns that the timeline was slipping.

    “I had hoped it would only be a couple of months at worst, and that we would see the EAF operating in spring 2028,” he said.

    “It now appears that that was too hopeful, and it is now moving into autumn 2028 before the EAF is operational.”

    That timeline goes further than Tata’s own public position, which put the likely delay at six to eight months.

    Rees called on the UK and Welsh governments to commit to getting the furnace running as quickly as possible and to minimise any further delay.

    He said they “must get National Grid to guarantee this, and pay penalties if they fail to do so”.

    The electric arc furnace is central to the future of steelmaking in Port Talbot, replacing the blast furnaces that closed in 2024 with the loss of around 2,000 jobs.

    It is designed to make lower-carbon “green steel” by melting scrap in an electric furnace rather than burning coal — but it needs a major grid upgrade to power it.

    “We all want to see steel once again being produced in Port Talbot, and it is imperative that this is done as soon as possible,” Rees said.

    “Our town and workers deserve nothing less.”

    Related stories from Swansea Bay News

    GREEN STEEL: Port Talbot’s £1.25bn furnace could be delayed by up to eight months over power hold-up
    Tata’s warning over the delayed grid connection.

    ‘Green power’ boost for Port Talbot as council green-lights major substation expansion
    The substation upgrade central to powering the new furnace.

    STEELWORKS FIRE: Tata says blaze restricted to ‘confined area’ of Cold Mill
    A separate fire at the site earlier this month.

    PORT TALBOT: Tata Steel sets out demands for next Welsh Government
    The wider £1.25bn transformation and its impact on jobs.

    #DavidReesMS #electricArcFurnace #greenSteel #industry #NationalGrid #PortTalbotSteelworks #TataSteel
  30. GREEN STEEL: Port Talbot’s £1.25bn furnace could be delayed by up to eight months over power hold-up

    Tata Steel’s switch to “green steel” at Port Talbot could be delayed by up to eight months, the company has warned — because of problems connecting its new furnace to the power network.

    The £1.25bn electric arc furnace, which will make lower-carbon steel by melting scrap rather than burning coal, was due to be running by the end of 2027 — replacing the blast furnaces that closed two years ago with the loss of around 2,000 jobs.

    But the project now hinges on a major upgrade to the electricity network — and that work has hit problems.

    The new furnace will melt scrap steel using huge amounts of electricity, rather than the coal-fired blast furnaces it replaces, and securing enough power is critical to the switch.

    Tata is working with the National Grid to build the infrastructure needed to feed it.

    Port Talbot from above with the town’s steelworks in the distance (Image: Neath Port Talbot Council)

    The warning came from the company’s executive director and chief financial officer, Koushik Chatterjee, during a conference call with investors last month.

    Chatterjee said major demolition work on the site had been completed and the project was progressing, but that “securing access to high power electricity is critical for our planned transition”.

    He said the National Grid had “formally alerted us that their connectivity project is delayed”, and that Tata was in talks with the grid operator and the UK government to resolve the issue.

    Asked how long the hold-up might be, he said: “Somewhat between, say, six months to eight months will certainly be there, maybe higher, after we have built the plant.”

    In a statement, Tata said timelines for major projects “continue to evolve” as engineering, construction and infrastructure work progresses.

    The company said it was discussing “potential adjustments to the commissioning timetable” with its partners to deliver the project “safely and as quickly as possible”.

    Massive ladles and overhead cranes inside Port Talbot steelworks, as Tata prepares the site for Electric Arc Furnace installation. (Credit: Tata Steel)

    The scale of the grid work is considerable. The National Grid said it involved building two new substations, installing transformers and laying 2km of underground cables.

    It said issues with ground conditions, along with environmental and planning considerations, had contributed to the delays, but that “good progress” was being made.

    Much of that work has already been visible across Port Talbot. Earlier this year the council approved a major expansion of a substation described as “nationally important” to the steel project.

    Motorists have also faced up to a year of roadworks as the underground electricity network is upgraded to carry the extra load.

    The delay is the latest twist in a turbulent period for the works, which is partway through a £1.25bn transformation that has already cost thousands of jobs.

    The setback comes during a difficult spell for the works. Days earlier, a major fire tore through a processing line at the site, leaving part of a building collapsed.

    The company said the blaze had forced its Hot Strip Mill offline, with a restart planned for the middle of next week, and that it was routing some work through its Llanwern site to keep supplies flowing to customers.

    Tata says the electric arc furnace remains central to its plans for steelmaking in Port Talbot — but for now, the question is when, not if, it will fire up.

    Related stories from Swansea Bay News

    PORT TALBOT: Tata Steel sets out demands for next Welsh Government
    The backdrop of thousands of jobs lost as the £1.25bn transformation presses ahead.

    ‘Green power’ boost for Port Talbot as council green-lights major substation expansion
    The substation upgrade central to powering the new electric furnace.

    STEELWORKS FIRE: Tata says blaze restricted to ‘confined area’ of Cold Mill
    A major fire tore through a processing line at the site days earlier.

    #electricArcFurnace #NationalGrid #PortTalbotSteelworks #TataSteel
  31. EU Scrap Market 2025: Decline Slows, Exports Rise, Green Transition Shapes Long-Term Demand | GMK Center Report – News and Statistics

    May 6, 2026 The EU scrap market in 2025 continued to feel the effects of a weak steel…
    #Europe #EU #Egyptscrapimports #electricarcfurnace #EUscrapmarket #EuropeanUnion #GMKCenter #greentransition #scrapdemand #scrapexports #scrapprices #steelproduction #Turkeyscrapimports
    europesays.com/europe/32817/

  32. PORT TALBOT STEEL GETS NEW ROLE IN GREEN ENERGY FUTURE: Welsh consortium launches research into wind turbine towers made with local steel

    Researchers backed by Welsh Government funding have launched a project that could see the steel being made in Port Talbot’s new electric arc furnace used to build the next generation of wind turbine towers — creating a direct link between the town’s industrial future and Wales’s clean energy ambitions.

    The consortium, led by the Offshore Renewable Energy Catapult, includes Tata Steel UK, energy companies RWE and Bute Energy, and engineering firms Hutchinson Engineering and Ledwood. It has been awarded £174,000 through the Welsh Government’s SMART Flexible Innovation Support scheme to research a new approach to turbine tower design using thin strip, coil-based steel produced in low-emission electric arc furnaces.

    The significance for Port Talbot is immediate. Tata Steel is currently in the middle of a £1.25 billion transition from blast furnace steelmaking to electric arc furnace production — a transformation that has already cost thousands of jobs at the steelworks but which the company says will deliver a cleaner, more competitive future. As Swansea Bay News has reported extensively, construction of the new furnace is now under way, with commissioning expected by the end of 2027 or early 2028.

    The type of steel at the heart of this new research project — thin strip, coil-based product made in an electric arc furnace — is precisely the kind of output that Port Talbot’s new operation will be able to produce. That steel is also the feedstock that flows downstream to operations including the Trostre tinplate works in Llanelli, which produces coated steel for food and drink packaging and which is directly dependent on the Port Talbot supply chain.

    The turbine tower research aims to solve a specific problem in the UK’s renewable energy sector. Most wind turbine towers currently built in Britain rely on thick steel plate imported from overseas — creating a bottleneck in the supply chain and adding cost and carbon to projects. The consortium wants to develop a design that replaces imported thick plate with domestically produced thin strip coil steel, using engineering techniques borrowed from the marine and aerospace industries to create structures that are lighter, stronger and cheaper.

    Crucially, the proposed design would also be dismantlable and recyclable — meaning that when turbines reach the end of their working life, the steel could be melted down and reused. Bute Energy’s Catryn Newton described it as a circular economy vision for Welsh steel: end-of-life turbines helping to power homes and industry for decades could eventually be recycled through the electric arc furnace and transformed into the towers of the next generation.

    “If we get this right, we could see end of life turbines that have been helping to power homes and industry across Wales for the past 30 years, recycled and sent to the newer electric arc furnaces,” she said. “The work of this group is exploring whether that scrap metal can be transformed into a material that could be used in the next generation turbine towers, helping to power Wales’ clean power future.”

    Computer-generated perspective of how Tata Steel at Port Talbot will look once the new EAF (electric arc furnace) is fully completed.
    (Image: Tata Steel)

    Tata Steel’s Sumitesh Das said the company was excited to be involved in research that could position Wales as a global hub for this kind of innovation. “As Tata Steel UK transitions to electric arc furnace steelmaking, our ambition is to ensure domestic supply chains capitalise on the growth of clean energy and help drive economic growth in the UK,” he said.

    The project comes as Port Talbot’s industrial community continues to navigate the painful consequences of the blast furnace closures, which took around 2,800 jobs with them. The hope — articulated by politicians, unions and the company itself — has been that the new electric arc furnace would not only preserve steelmaking in the town but open doors to new markets and new applications for Welsh steel. This wind tower project is one of the first concrete examples of what that future might look like in practice.

    Aberafan Maesteg MP Stephen Kinnock welcomed the research, saying it was essential that British and Welsh steel played a central role in the clean energy transition. “This research demonstrates how Wales and the UK can remain at the forefront of the transition to renewable energy,” he said. “By decreasing reliance on imported steel we can bolster energy security, create economic growth, secure regional jobs, and support offshore wind deployment in the Celtic Sea and beyond.”

    Rebecca Evans MS, Cabinet Secretary for Economy, Energy and Planning, said the investment reflected the Welsh Government’s commitment to building a greener economy. She pointed to the potential for creating high-value jobs and strengthening supply chains as Welsh industry pivots towards clean energy.

    The Celtic Sea, off the coast of Pembrokeshire and west Wales, is one of the most promising sites for floating offshore wind development in the UK. Port Talbot — with its established steel expertise, its port infrastructure and its proximity to that potential wind farm zone — has long been identified as a natural base for offshore wind supply chain activity. As Swansea Bay News has reported, a £64 million wind energy hub plan for Port Talbot has already been put forward with the promise of up to 5,000 jobs.

    The first phase of the new research project will focus specifically on onshore turbine tower design and the commercial case for using locally produced coil steel. If the concept proves viable, the researchers say it could be extended to offshore and floating wind applications in later phases — potentially unlocking a significant new market for the steel being made in Port Talbot and processed downstream at Trostre.

    Related stories from Swansea Bay News

    Work begins on Port Talbot electric arc furnace as steelworks transition moves forward
    The groundbreaking that marked the start of building the very furnace this wind tower research is designed to feed.

    Inside the giant Port Talbot steelworks overhaul as Tata clears the way for new electric arc furnace
    An inside look at the transformation under way at the steelworks — and what it means for the future of steel in South Wales.

    Tata Steel begins new project at Port Talbot in £1.25bn green plan
    The pickle line that supplies Trostre in Llanelli — a reminder of how closely linked Port Talbot and the downstream operations are.

    PORT TALBOT POWER PLAY: £64m wind hub plan promises 5,000 jobs in major shake-up
    The wider vision for Port Talbot as a centre for clean energy — and how today’s research fits into that bigger picture.

    #electricArcFurnace #OffshoreRenewableEnergyCatapult #PortTalbot #PortTalbotSteelworks #steel #TataSteel #TataSteelworks #WelshSteel #windTurbine
  33. PORT TALBOT: Steel plan sparks cautious hope — but big questions remain for Welsh jobs

    At the heart of the strategy is a push to rebuild domestic steelmaking, including new tariffs on imports, a target for half of UK steel demand to be met at home, and billions in funding to support the industry’s transition.

    For communities built around steel, the announcement lands at a critical moment.

    In Port Talbot, the shift away from traditional blast furnaces is already under way, while in Llanelli, the Trostre works continues to play a key role in Welsh production. Together, they form part of an industry now facing one of the biggest changes in its history.

    Local Labour MP Dame Nia Griffith has backed the plan, arguing it signals a more serious commitment to the sector after years of uncertainty.

    Dame Nia Griffith, MP for Llanelli, said:
    “The steel industry is a vital core element of our economy here in Wales, generating growth and providing thousands of jobs, including hundreds in my own constituency.

    “This is a clear, well thought-out, long-term strategy for our steel industry that will help deliver the high-quality steel our country needs for our key infrastructure, our national security and for the wider economy.”

    Her support reflects the Government’s central message — that the strategy will not only protect jobs, but put the industry on a more stable footing for the future.

    But that optimism is far from universal.

    Opposition figures say the plan raises as many questions as it answers, particularly around how much of the promised investment will reach Wales and what role UK steel will play in major future projects.

    Trostre Steel Works in Llanelli (Image: Tata Steel)

    David Chadwick MP, Liberal Democrat spokesperson for Wales, said:
    “It is welcome that the Government has finally acted, but this looks like a panicked move after months of delay.

    “Since the blast furnaces were switched off, Welsh steel has been left on life support.”

    There are also concerns about the UK’s trading position, with warnings that being outside key European arrangements could leave exporters at a disadvantage in one of their biggest markets.

    Industry voices have struck a similarly measured tone — welcoming steps to tackle cheap imports while warning that deeper issues remain unresolved.

    Unite, which represents many steelworkers across Wales, says the new tariff regime is a positive step, but argues the industry needs a clearer long-term direction.

    Sharon Graham, General Secretary of Unite, said:
    “Unite welcomes the strengthening of the UK’s tariff regime to prevent the dumping of cheap foreign steel onto the domestic market.

    “But this last minute situation is just another reminder that the reactive approach to UK steel that sees it lurch from crisis to crisis needs to be overhauled.”

    One of the biggest sticking points is the industry’s shift towards electric arc furnaces — a cleaner form of steelmaking that relies heavily on recycled materials.

    While central to the Government’s net zero ambitions, unions have warned that relying too heavily on this approach could limit the UK’s ability to produce certain types of steel.

    The hot mill at Tata Steel’s Port Talbot steelworks. (Image: Tata Steel)

    Peter Hughes, Unite regional secretary, said:
    “The government must also back the production of virgin green steel as we can’t simply rely on electric arc furnaces to produce all the steel we need.”

    Alongside the strategy, ministers have also unveiled a new funding stream aimed at helping areas like Port Talbot adapt to the changes.

    The Economic Growth & Investment Fund will offer grants of up to £1.5 million to businesses across Neath Port Talbot, Swansea and Bridgend, targeting sectors such as advanced manufacturing, green energy and digital industries.

    Local leaders say it could help soften the economic impact of the transition — if it delivers.

    Neath Port Talbot Council leader Cllr Steve Hunt looks out across Port Talbot Steelworks from a hillside vantage point, reflecting on the town’s industrial past and future.
    (Image: Neath Port Talbot Council)

    Cllr Steve Hunt, Leader of Neath Port Talbot Council, said:
    “This fund provides an important opportunity to support businesses that are ready to invest, grow and create new jobs across the region.”

    For now, the strategy marks a significant moment for Welsh steel — but not a settled one.

    With major changes already under way and more still to come, the focus is quickly shifting from what has been promised to what will actually be delivered.

    And for communities across South West Wales, that will ultimately be the measure that matters most.

    Related stories from Swansea Bay News

    One year on: resilience after blast furnace closure
    Council leaders reflect on a turbulent year for the steel town.

    Work begins on Port Talbot electric arc furnace
    A major step in the steelworks’ transition to new technology.

    Farage promises “reindustrialisation of Wales”
    A headline‑grabbing pledge to revive coal and steel sparks debate.

    Government criticised over treatment of steelworkers
    Unions and politicians condemn support offered during the transition.

    Dramatic video shows final push at Morfa coke plant
    Striking footage captures the last days before shutdown.

    #DavidChadwick #electricArcFurnace #industrialStrategy #JoStevens #Llanelli #NeathPortTalbotCouncil #NiaGriffith #PeterHughes #PortTalbot #SharonGraham #SouthWestWalesEconomy #steelJobsWales #TataSteel #Trostre #UKGovernment #UKSteelStrategy #UniteUnion #WelshEconomy #WelshSteel
  34. PORT TALBOT: Government vows to “do whatever it takes” to protect steel jobs — but critics warn over end of traditional steelmaking

    A major new Steel Strategy has been unveiled during a visit to Port Talbot, with ministers promising tougher trade rules, billions in investment and a push to increase the amount of steel made in Britain.

    At the centre of the plan is a target for 50% of all steel used in the UK to be made domestically — up from around 30% — with the Government saying Welsh producers are expected to play a major role.

    That includes Tata Steel operations in Port Talbot, Llanelli, Shotton and Newport, as well as 7Steel in Cardiff.

    The UK Government says it will also crack down on cheap imports.

    From July, steel import quotas would be cut by 60%, with anything above those limits facing a 50% tariff.

    Ministers argue the move will stop British steel being undercut — a long-standing complaint from workers and industry leaders in South Wales.

    But the strategy has already sparked debate about what kind of steel industry the UK is actually protecting.

    Massive ladles and overhead cranes inside Port Talbot steelworks, as Tata prepares the site for Electric Arc Furnace installation. (Credit: Tata Steel)

    While ministers are backing domestic production, the plans also confirm a continued shift away from traditional blast furnaces towards electric arc furnaces, like the one being built in Port Talbot.

    These use recycled scrap metal rather than raw materials — a move the Government says is key to cutting emissions and modernising the industry.

    However, critics warn that transition could come at a cost.

    They argue electric arc furnaces cannot always produce the same specialist grades of steel needed for defence and major infrastructure, raising concerns about long-term capability.

    There are also fears the UK could become more reliant on imported materials — even as ministers move to restrict finished steel imports.

    Peter Kyle, Business and Trade Secretary, said steelmaking was “vital” to the UK’s future.

    He said: “Making steel in the UK is vital for national security, critical infrastructure and the wider economy.

    “With this strategy we are closing the decades-long chapter of destructive de-industrialisation and committing instead to strengthening and sustaining Britain as a steel-making nation.”

    The Government says the strategy is backed by major investment, including £5.8 billion through the National Wealth Fund for priority industries such as steel.

    That builds on more than £600 million already committed to Port Talbot, alongside plans to unlock up to £2.5 billion in further funding during this Parliament.

    Jo Stevens, Secretary of State for Wales, said the plans showed ministers were standing firmly behind Welsh industry.

    She said: “The UK Government is standing up for Welsh steelmaking and showing that we will do whatever it takes to boost domestic steel production and protect the thousands of steelmaking jobs in our communities.

    “Welsh steel is expected to account for half of future UK steelmaking… Welsh steelmaking now has a secure and bright future.”

    The strategy also includes measures to lower energy costs, prioritise UK-made steel in public projects and strengthen links with sectors like offshore wind, defence and infrastructure.

    A new working group will also look at securing long-term supplies of scrap metal — a key part of the shift towards electric arc production.

    The move comes after years of uncertainty for the industry, with global competition, rising costs and the transition to greener production putting pressure on steelmaking communities across South Wales.

    Ministers insist imports will still play a role, but say the new rules are designed to strike a balance between protecting domestic producers and maintaining supply.

    However, with the industry undergoing one of its biggest transformations in decades, questions remain over whether the strategy will truly secure the long-term future of steelmaking in Wales — or simply reshape it.

    Related stories from Swansea Bay News

    One year on: resilience after blast furnace closure
    Council leaders reflect on a turbulent year for the steel town.

    Work begins on Port Talbot electric arc furnace
    A major step in the steelworks’ transition to new technology.

    Farage promises “reindustrialisation of Wales”
    A headline‑grabbing pledge to revive coal and steel sparks debate.

    Government criticised over treatment of steelworkers
    Unions and politicians condemn support offered during the transition.

    Dramatic video shows final push at Morfa coke plant
    Striking footage captures the last days before shutdown.

    #BritishIndustry #Economy #electricArcFurnace #featured #industry #JoStevens #jobs #Llanelli #manufacturing #netZero #PeterKyle #PortTalbot #PortTalbotSteelworks #southWales #steel #steelIndustry #steelStrategy #steelworks #TataSteel #TataSteelworks #Trostre #TrostreSteelworks #UKGovernment #WelshSteel
  35. ‘Green power’ boost for Port Talbot as council green-lights major substation expansion

    Neath Port Talbot Council has unanimously approved the major application from National Grid to extend the Margam 275kV substation, located just off Harbour Way.

    The project is being hailed as a “key” development that will provide the essential power needed for Tata Steel’s new £1.25 billion electric arc furnace. It follows the appointment of Sir Robert McAlpine as the main contractor for the site’s decarbonisation.

    This latest approval comes as Port Talbot motorists already face up to 12 months of roadworks while the wider underground electricity network is upgraded to support the transition.

    Council bosses have confirmed that the extended site will connect via underground cables to a separate substation within the Tata Steelworks, feeding the new “green” furnace. Work has already begun on the furnace project, which aims to replace the traditional blast furnaces.

    The works at the Margam site will include the construction of a new gas-insulated switchgear hall and a modern control building, replacing older facilities.

    Planning officers have confirmed that the project also includes significant upgrades to site lighting, CCTV, and internal access roads, along with a new flood defence wall.

    Cllr Rob Jones, representing Margam and Taibach, has described the extension as a “key project” that is essential for the survival of the local industry.

    “Without this substation extension taking place… the whole future of steelmaking in Port Talbot and the county borough is at serious risk,” Cllr Jones has warned.

    The council has confirmed that the approval is subject to a legal agreement to maintain an off-site ecological management area for the next 30 years to protect local wildlife.

    While the substation does not directly supply residential homes in Margam, its role in supporting the major infrastructure upgrade is seen as critical for the region’s economic future.

    The move marks another significant milestone for the electric arc furnace project, which was first approved by Neath Port Talbot Council in February 2025. The transition follows the dramatic closure of the Morfa Coke Plant and the blast furnaces, which saw thousands of jobs put at risk. Despite the £500m UK Government funding to support the move, the community continues to show resilience amid the transition.

    #Business #electricArcFurnace #greenEnergy #Infrastructure #Margam #NationalGrid #NeathPortTalbotCouncil #PortTalbot #roadworks #TataSteel
  36. Inside the giant Port Talbot steelworks overhaul as Tata clears the way for new Electric Arc Furnace

    The video, posted on Tata’s Facebook page, takes viewers back inside the vast BOS Plant — once the beating heart of blast furnace steelmaking — where crews are tearing out decades‑old infrastructure to make way for the new low‑carbon process.

    The update shows huge sections of the former hot metal and charging bays stripped back to bare concrete, with legacy equipment, weighing stations, diesel points and even the giant charging cranes now being dismantled. The cavernous building, once filled with molten iron and the roar of converters, is described as “a cathedral” now reduced to a shell as enabling works accelerate.

    Project engineers explain that the cleared space will become the EAF shell workshop, where the furnace’s massive components will be assembled and maintained. At the south end of the plant, contractors Sir Robert McAlpine are preparing the installation zone for the furnace itself — a transformation that involves digging out old pits, levelling entire bays and installing new piling across the site.

    Tata says the work is “laying the foundations for a new, low‑CO₂ steelmaking process” and marks the next chapter of UK steelmaking. The company insists the EAF will secure the long‑term future of the site, even as thousands of traditional steelmaking jobs disappear.

    Demolition and site clearance underway at Port Talbot steelworks, making way for Tata’s new low-carbon steelmaking process. (Credit: Tata Steel)

    A year of upheaval for steelworkers

    Over the past year, Swansea Bay News has followed every twist in Port Talbot’s steel saga. What began with warnings of weak demand soon spiralled into a series of hammer blows for workers — from Christmas shutdowns that slashed pay packets to the announcement that 2,800 jobs were at risk as Tata confirmed its plan to close the blast furnaces.

    The uncertainty has fuelled political rows in Cardiff and Westminster, with unions accusing Tata of refusing to wait for Labour’s promised investment and MPs warning of a “betrayal” of steel communities. EU tariffs, global market pressures and soaring costs have only deepened the crisis.

    At the same time, the company has pressed ahead with its £1.25bn green transition, signing contracts for new technology, appointing Sir Robert McAlpine to lead the decarbonisation build, and beginning early works on the Electric Arc Furnace. Government funding has been announced, retraining schemes launched, and start‑up grants rolled out to help families prepare for life after steel.

    Communities have shown resilience — from welding academies retraining former workers to local leaders fighting to protect jobs — but the financial strain on households has been impossible to ignore. And as demolition crews move through the plant, the physical dismantling of the old steelworks has become a stark symbol of the upheaval facing the town.

    Inside the BOS Plant: a steel cathedral stripped bare

    In the new video, engineers walk viewers through the vast BOS Plant, pointing out where the old weighing stations, fume hoods, diesel points and hot metal pits once stood. Much of the floor has been ripped up, leaving gaping holes where equipment sat for decades.

    The removal of the south charging crane — a job so large it requires opening the roof and bringing in a giant external crane — is described as a “huge undertaking”. The north crane was once installed the same way.

    Long‑serving staff speak openly about the emotional toll of dismantling equipment they helped install 35 years ago, even as they acknowledge the need to move forward.

    South end transformation: where the new furnace will rise

    The video then moves to the south end of the plant, now controlled by Sir Robert McAlpine. The area is almost unrecognisable. Entire bays have been stripped out, old scrap‑handling areas flattened, and deep pits dug out to prepare for the new furnace and ladle metallurgy stations.

    Engineers explain how the EAF will sit in the south‑west corner, with new transfer tracks linking the furnace, the ladle furnaces and the caster. Massive piling work will be needed across the entire building to support the new equipment.

    Even in its stripped‑back state, the layout of the future steelmaking process is beginning to emerge.

    A new era — but at a heavy cost

    Tata says the EAF will cut emissions dramatically and modernise the plant, but unions warn the shift will slash jobs and leave the UK dependent on imported steel scrap. The company has already confirmed that large parts of the works will close permanently this year.

    Despite the upheaval, Tata insists progress is “well underway behind the scenes” and promises more updates as the project moves forward.

    The next major milestone will be the arrival of the EAF shell and equipment — a moment that will symbolise the end of one era of Welsh steelmaking and the beginning of another.

    More Tata Steel Coverage

    Work begins on Port Talbot Electric Arc Furnace
    Early construction marks the start of the site’s green steel transition.

    2,800 jobs at risk as Tata announces plans
    Workers brace for major changes as blast furnaces face closure.

    Tata confirms closure of part of Port Talbot steelworks
    Sections of the plant shut down as transition accelerates.

    Steelworkers face ‘catastrophic’ Christmas pay cuts
    Extended shutdown leaves families struggling over the festive period.

    Port Talbot communities show resilience amid transition
    Local support grows as financial pressures mount on households.

    Tata signs contract for green steelmaking technology
    New equipment deal paves the way for low‑carbon production.

    Union prepares to escalate industrial action
    Anger grows as Tata pushes ahead without waiting for government support.

    #BOSPlant #EAFShellWorkshop #electricArcFurnace #greenSteel #industry #lowCOSteelmaking #PortTalbot #PortTalbotSteelworks #TataSteel #TataSteelworks
  37. Tata Steel begins new project at Port Talbot in £1.25bn green plan

    The company says the state‑of‑the‑art facility will replace ageing equipment and prepare hot rolled steel for downstream processes. The line cleans and treats steel before it is cold rolled and coated, supplying other Tata operations at Trostre, Llanwern and Shotton.

    A turning point for Tata’s operations

    Mills Programme Manager Andrew McGregor called the groundbreaking a turning point.

    “This is a fundamental asset that is required for us to have a sustainable UK business going forward,” he said.

    “Our current assets are at the end of their operational life, and without this replacement pickle line, we wouldn’t be able to process many of the steels required for our downstream businesses and directly for our customers.”

    McGregor also praised the project team for months of preparatory work, from diverting cables to clearing the bay, which has allowed demolition crews to move in.

    Tata Steel executives, including Pramod Agrawal and Rajesh Nair, inspect the cleared bay inside Port Talbot steelworks where the new pickle line will be built.(Image: Tata Steel)

    One year after the blast furnaces fell silent

    The investment comes less than a year after the closure of Port Talbot’s blast furnaces, which brought significant job losses and uncertainty for the town. Tata insists the pickle line is a sign of renewal, but unions and community leaders have warned that the transition to electric arc furnace production will still mean a smaller workforce.

    The new pickle line is scheduled to be in place by 2026, ahead of the planned commissioning of a 3.2 million‑tonne electric arc furnace in 2027/28. Tata says the EAF will melt UK‑sourced scrap steel and form the centrepiece of its decarbonisation strategy.

    Project leaders and contractors gather in hi‑vis at Port Talbot steelworks as demolition begins for the new pickle line, alongside heavy machinery on site.(Image: Tata Steel)

    Local firms in the frame

    Construction of the pickle line is being led by Sir Robert McAlpine, with regional firms including Darlow Lloyd & Sons, Andrew Scott Ltd and Systems Group also involved.

    At the official ceremony, Tata Steel board member Pramod Agrawal cut the ribbon alongside senior executives.

    Pramod Agrawal, Tata Steel board member, during his visit to Port Talbot to mark the start of the new pickle line project.(Image: Tata Steel)

    Optimism tempered by caution

    For Port Talbot, the start of work on the pickle line is another reminder of the site’s changing role. Neath Port Talbot Council leader Steve Hunt recently described the past year as “seismic” for the town, but said projects such as the pickle line and the Celtic Freeport offered reasons for optimism.

    Campaigners, however, remain cautious. They argue that while new investment is welcome, the loss of traditional steelmaking has left deep scars and that promises of a “green future” must be matched by secure jobs and long‑term commitments.

    Related articles

    #AndrewScottLtd #blastFurnace #DarlowLloydSons #electricArcFurnace #GreenSteelmaking #industry #manufacturing #PickleLine #PortTalbot #PortTalbotSteelworks #PramodAgrawal #SirRobertMcAlpine #SystemsGroup #TataSteel

  38. Powering change: National Grid sets out plans to electrify green steel in Port Talbot

    National Grid has announced plans for a major electricity infrastructure upgrade in Port Talbot to power Tata Steel’s new electric arc furnace (EAF) and strengthen energy capacity across South Wales.

    The Margam Connection Project includes the expansion of the existing Margam substation with a new 275kV gas-insulated substation (GIS), and a second GIS facility at the Tata Steel site connected via underground cable. Both sites will be built using SF6-free switchgear technology, reducing the project’s environmental footprint.

    A public information event will take place on Thursday 17 July, from 2pm to 8pm, at Margam Community Centre, Bertha Road, Port Talbot, ahead of a 28-day statutory pre-application consultation.

    Richard Gott, project director at National Grid Electricity Transmission, said the upgrade will help deliver a cleaner, more secure energy future for South Wales. “By enabling the electrification of Tata Steel’s operations, we’re not only supporting the UK’s transition to green steel but also helping to safeguard jobs and strengthen the local economy,” he said. “We look forward to engaging with the community and hearing their views.”

    Construction will be delivered in partnership with Laing O’Rourke, using pioneering technology that replaces sulphur hexafluoride (SF6)—a commonly used but potent greenhouse gas—with lower-impact alternatives.

    Peter Lyons, managing director for Laing O’Rourke’s Europe hub, said the firm was proud to continue its partnership with National Grid. “This project is another fantastic example of how we’re helping to deliver cleaner and more secure energy for the UK,” he said. “Through early collaboration, we’ve worked together on the design and implementation programme, and National Grid has valued both our unique operating model and our technical expertise.”

    National Grid is planning £35 billion of transmission network investment across Wales and England between 2026 and 2031 to connect clean power sources, electrify industry, and support national economic growth.

    Related stories from Swansea Bay News

    Tata Steel breaks ground on new electric arc furnace in Port Talbot
    Construction begins on low-carbon steelmaking facility set to transform the future of Welsh steel.

    Port Talbot steelworkers to be offered redundancy packages as part of green transition
    Tata Steel outlines support measures for workers affected by shift to electric arc furnace technology.

    First Minister visits Port Talbot to meet steelworkers and discuss green jobs
    Welsh Government pledges support for workforce and future investment in sustainable industry.

    Steel unions call for alternative plan to save jobs at Port Talbot
    Union leaders urge Tata Steel to reconsider proposals and protect long-term employment in the region.

    #electricArcFurnace #electricitySubStation #greenSteel #LaingORourke #Margam #NationalGrid #PortTalbot #PortTalbotSteelworks #powerLines #TataSteel

  39. Work begins on Port Talbot electric arc furnace as steelworks transition moves forward

    Construction has begun on Tata Steel’s £1.25bn electric arc furnace (EAF) in Port Talbot, marking a major milestone in Wales’ industrial transformation—but it comes with the loss of more than 2,800 jobs and the end of traditional steelmaking in the town.

    Business Secretary Jonathan Reynolds, Welsh Secretary Jo Stevens, and Tata Group Chairman Natarajan Chandrasekaran formally broke ground at the steelworks site on Monday (14 July), signalling the start of a project designed to cut carbon emissions by 90% and shift production toward recycled scrap steel.

    The UK Government has committed £500 million toward the EAF, describing it as “a major win” for Welsh steelmaking that secures 5,000 jobs nationwide. The new furnace will replace the site’s two blast furnaces—shut down in September 2024—ending a century of primary steelmaking in Wales.

    ‘Bitter sweet’ day for steelworkers and families

    The announcement has been widely described as bittersweet. While Tata and ministers hailed the start of a cleaner, greener future, union representatives and local leaders stressed the impact of the redundancies and the uncertainty still facing thousands of workers.

    Assistant General Secretary Alasdair McDiarmid of Community Union said:

    “This bittersweet day is a consequence of the devastating closure of the blast furnaces, but importantly a future for Port Talbot steelmaking is being secured.

    The workforce needs the electric arc furnace project to be both a success and a turning point… Going forward we must see further investment to develop and grow the business, both here in Port Talbot and across all the crucial downstream sites.”

    Speaking ahead of the groundbreaking, First Minister Eluned Morgan said the construction phase represents “a tangible sign” of Tata’s commitment, adding that the Welsh Government is working with partners to support affected workers and promote economic resilience.

    Former steelworker Graham Rowland said:

    “I’ve seen good boys lose their jobs… This industry kept this town alive. It’s the heart and soul of the place. If anywhere can make that arc work, it’s Port Talbot. The knowledge, the grit, the people—it’s all here. We just need the right support.”

    Related stories from Swansea Bay News

    Job losses confirmed as Tata Steel sets timetable for blast furnace closures
    Explores the closure of Port Talbot’s heavy-end and its impact on workers.

    Port Talbot regeneration fund launched to support steelworker transition
    Details funding pledged to support displaced workers and local communities.

    Celtic Freeport: what it means for the local economy and green infrastructure
    Examines future investment opportunities connected to Port Talbot’s green transition.

    EAF: cleaner steel, fewer emissions—but far fewer jobs

    Tata Steel says the new furnace is essential to achieving climate targets and creating “a financially and environmentally sustainable future.” The company has reported losses of £4bn in Port Talbot since 2007.

    Chairman Natarajan Chandrasekaran said:

    “This is a proud day for the Tata Group, Tata Steel and for the UK. At Port Talbot we are building the foundations of a cleaner, greener future—supporting jobs, driving innovation and demonstrating our commitment to responsible industry leadership.”

    The new furnace will be built on the site of the Basic Oxygen Steelmaking (BOS) plant and is set to be one of the largest of its kind globally, capable of producing up to three million tonnes of steel per year. Contractor Sir Robert McAlpine has been appointed to deliver the build, which will also include a new scrap processing plant.

    Operations are expected to begin in late 2027. In the meantime, Port Talbot will continue to roll imported steel slabs through its hot strip mill and finishing lines.

    Supporting workers through the transition

    Neath Port Talbot Council and the Tata Steel / Port Talbot Transition Board have pledged over £100 million to support workers, businesses and community recovery. This includes:

    • A £19.8 million Employment and Skills Fund
    • A £21.2 million investment in Harbourside manufacturing and skills facilities
    • A £13 million business start-up and resilience programme
    • Additional community grants targeting financial hardship, mental health and career retraining

    A recent survey by Public Health Wales found that 74% of local households expect to face financial pressure in the coming months, with food, energy, and housing cited as key concerns.

    Council Leader Cllr Steve Hunt said:

    “On behalf of the Transition Board, Neath Port Talbot Council is delivering targeted support to people and businesses both within Neath Port Talbot and further afield.”

    Looking ahead

    While the shift to EAF production represents a landmark shift in Welsh industry, many argue the transformation must be judged not just by its carbon savings, but by the long-term outcomes for workers, communities and supply chains.

    Luke Fletcher MS, Economy spokesperson for Plaid Cymru and Senedd Member for South Wales West, said the start of construction is “welcome,” but warned that “the opportunity has been lost to safeguard over 2,000 primary steelmaking jobs.”

    “Labour has promised a lot to the communities in and around Port Talbot,” he said, “it’s vital that those promises are realised now.”

    Swansea Bay News will continue to follow developments across Port Talbot and the steel sector as this historic transition unfolds.

    #CllrSteveHunt #CommunityUnion #electricArcFurnace #ElunedMorganMS #featured #LukeFletcherMS #NatarajanChandrasekaran #PortTalbot #PortTalbotSteelworks #steelworks #TataSteel